Horizon Mission Bay | Construction Update

The start of 2019 has seen substantial progress on site at Horizon Mission Bay.

Construction is tracking well, with all piling now finalized. This included the completion of 122 retaining piles and 13 piles for the plunge columns, to enable the top down construction methodology.

The pouring of concrete for the tower crane base and one of the lift pits is now complete, making way for the crane election at the beginning of March.

Soil removal from site has now reached over 10,000m3 to date, with a detailed dig for foundations due to commence shortly.

We look forward to bringing you our next update with all the latest progress taking place on site.